Severn Trent Water is undertaking the development of a new Wastewater Treatment Plant for the village of Loggerheads in Staffordshire. Upon completion, the Loggerheads site will have a capacity of approximately 3,700 PE (Population Equivalent) and the treated effluent quality will comply with the new phosphorous consent permit.
Home »
Loggerheads STW
Project Overview
Early collaborative meetings led to the delivery of the scheme’s two Primary Settlement tanks as a turnkey package. Our 360° Package solution included:
- The design and on-site construction of two conical concrete tank bases incorporating central hoppers.
- ULTRASTORE® Tanks featuring our newly developed Stainless Steel internal Launder systems.
- Due to the site’s hydraulic design, the Primary Settlement Tanks needed to be partially buried below ground, necessitating bespoke designs for both the concrete base and the tank walls.
- Our in-house designed half bridge scraper system.
Project Headlines
- Cost Reduction: Eliminates the traditional “fee on fee on fee” structure.
- Accelerated Programmes: Sequential activities minimize time on site.
- Interface Issue Elimination: Our in-house model ensures all elements are designed and installed by Stortec.
- Sustainability Promotion: Innovative products and approaches combine to provide sustainable solutions.
All elements of the project were delivered using our in-house resources.
Client
Severn Trent Water
End User
Severn Trent Water
Value
- £560,000.00
Scope
Supply & Installation of 2-OFF
Primary Settlement Tanks
Tank
- 2-OFF Primary Settlement Tanks
Diameter
- 8,539mm
Height
- 2,718mm
Volume
- 127m³